Dock Repair in Boca Raton
Dock repair in Boca Raton runs through the city's own plan review and inspections. This is what the city asks the contractor to show.
Get a free match
Call or text (561) 668-0871
Call now or send a text with your address and what you need.
The following is required information on plans to be provided by the contractor during both plan review and inspection stages:
Plan Review:
Survey (current conditions)
- Existing seawall wetface/bulkhead line
- Property line
- Location of existing seawall wetface, piles, and marine structure(s)
Section detail(s)
- Existing seawall wetface/bulkhead line
- Property line
- Measurement from edge of seawall cap to property line and seawall wetface
- Measurement from edge of marine structure to property line and seawall wetface
- Identify existing and proposed seawall panel
- Identify existing and proposed piles
- Elevation/details of finished top of seawall cap
Proposed Construction Site Plan/Survey
- Existing seawall wetface/bulkhead line
- Property line
- Location of section detail(s)/piles
- Measurement from edge of seawall cap to property line and seawall wetface
- Measurement from edge of marine structure to property line and seawall wetface
Inspections:
Seawall Marine Structures (docks, boatlifts, etc.) 1 ZON – Location Survey:
- Seawall wetface/bulkhead line
- Property Line
- Location of piles
- Must be inspected before cap is installed
- Must be approved prior to scheduling structural cap and piling inspections
ZON – Location Survey:
- Seawall wetface/bulkhead line
- Property Line
- Measurement from piles to property line and seawall wetface
- Location of piles
- Must be inspected the before framing inspection
2 ZON – Final Engineer Report:
- Seawall cap elevation
- Compliance with permit drawings
- Photos of completed seawall
- Must be provided after construction
ZON – Final Marine Structure Survey:
- Seawall wetface/bulkhead line
- Property Line
- Measurement from marine structure to property line and seawall wetface
- Location of piles
- Must be inspected after construction
*If scope of work includes both seawall and marine structures, then all 3 inspections apply:
- ZON – Location Survey
- ZON – Final Marine Structure Survey
- ZON – Final Engineer Report
Pulled Nov. 21, 2026.
See the right column? Piles and distances get checked before framing and again after construction.
How high, and how far out?
The city's design manual answers both. Item 1 is the height range for a new or replaced dock.
7.7 MINIMUM CRITERIA FOR WATERWAY FEATURES
The City’s Coastal Management Section Policy CM.1.1.11 includes enforcement of construction standards which minimize impacts of man-made structures on beach or dune systems. The minimum design criteria and layout of waterway features in this section applies to harbors, docks, bulkheads and seawalls.
Boat travel in coastal waters is a public right established through the commerce clause of the U.S. Constitution which gives Congress regulatory power over navigable waters. This authority that has been delegated to the U.S. Army Corps of Engineers (USACE). The USACE has published engineering manuals on topics such as Coastal Engineering, Shore Protection, Revetments, Seawalls, and Bulkheads, which can be used by the EOR for reference.
Design parameters are provided per Section 22 Marine Structures of the City Code and the American Society of Civil Engineers Manual of Practice No. 50 for Harbors and Docks, which can be used by the EOR for reference. The following standards reflect the ability to maintain a sustainable design with changing climate conditions:
1. The minimum elevation of any new or replaced seawall or dock (publicly or privately owned) is 4.0 feet NAVD88. The maximum elevation shall be 6.0 feet NAVD88.
2. The seawall shall be designed and constructed to harmonize with the adjacent grades and seawalls.
3. The seawall shall be designed and constructed to allow for an additional height of 12-18 inches be added in the future and remain structurally sound without alteration to the existing wall.
4. Hybrid shoreline infrastructure which incorporates gray features, such as seawalls, and living or nature-based elements should be considered.
7.7.1 CONSTRUCTION WITHIN THE WATERWAY
1. The determination of the bulkhead lines along all shores of the Intercoastal Waterway (F.E.C. Canal), the easterly shore of Lake Wyman, and Lake Boca Raton are established per Sec. 22-31 and 22-32 of the City Code.
2. Single family residential lots may have freestanding docks protruding no more than 6-8 feet water ward of the seawall (depending on the width of the canal refer to Section 22-58 of the City Code).
3. All structures must be placed within an area defined by projected lines extending water ward at a 45-degree angle from the property’s seawall at the side property lines.
4. Seawalls and bulkheads shall not be constructed beyond the property line. The section view of seawall components depicts key elements to be identified on the engineering drawings. The water side face (i.e. wet face) being on the property line per Sec. 26-146 of the City Code as depicted on the following example section.
Pulled Nov. 21, 2026. The manual follows this with a seawall section drawing on page 33.
Is it a repair under state law?
Within 5 feet of the old spot, no bigger, no fill.
(d) The replacement or repair of existing docks and piers, except that fill material may not be used and the replacement or repaired dock or pier must be within 5 feet of the same location and no larger in size than the existing dock or pier, and no additional aquatic resources may be adversely and permanently impacted by such replacement or repair. This does not preclude the use of different construction materials or minor deviations to allow upgrades to current structural and design standards.
Pulled Nov. 21, 2026.
The rest of that statute is on the permit page. Not sure it's still a repair? Read repair or replace.